Construction Update - April 19

Read more to see how your stage is progressing!

Welcome to the next edition of the Life, Point Cook Construction Update. We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community. Cleverly designed around a series of interconnected parks, conservation reserves and stunning wetlands, Life, Point Cook is your place to play and live life to its fullest. We can’t wait to make it a home for you and a welcoming haven for your family and friends.

Stage 12
Works continue to progress well. We have competed lot filling, sewer, drainage and water infrastructure. This week we are placing the pavement subbase and we will commence kerb prior to Easter. Titles are anticipated at the end of June 2019. With settlements expected in July 2019. 

Construction Update

Stage 13
We are currently completing the sewer infrastructure and drainage has also commenced. Lot filling is completed. Post the drainage we will commence the water infrastructure and road service crossings. Titles are anticipated in early September and settlements in late September 2019.

Construction Update

Stage 16

We have completed the sewer infrastructure and drainage is well advanced. Lot filling is completed. Road boxing will commence next week. Titles are anticipated in early September and settlements in late September 2019.

Construction Update

Wetlands 

You would have seen that we have started shaping up the wetlands on the southern boundary of the project. There are significant earthworks to be completed before we can start any landscaping works. The wetlands will create a great natural asset to the development with walking tracks and boardwalk on completion.

Construction Update