May 2019 | Construction Updates

May 2019 | Construction Updates

We are excitED to bring you the latest construction update on the progress of Ed.Square Town Centre. Good news…. Construction works are progressing well, running right on schedule!

With manpower reaching up to 350 workers onsite each day, 23,000m2 of formwork have been erected and 7,500m3 of concrete was poured on both the northern and southern ends of the Ed.Square Town Centre site during the month of May.

Based on the current construction program, it is anticipated that the first stage of the Ed.Square Town Centre will open in the second half of 2020 and will include a shopping, dining and entertainment precinct. 