Project Timeline

Stage 1 forecast completion Q4 2023

Residential apartments

Stage 1 roads

Stage 2 Forecast completion Q4 2025

Residential apartments,

Stage 2 roads

Main park

Community centre

Stage 3 forecast completion Q2 2026

Residential apartments

Shrimpton's creek rehabilitation

Part Endangered Ecological rehabilitation

Stage 4 forecast completion Q3 2027

Residential apartments

Forest playground

Part Endangered Ecological rehabilitation

Stage 5 forecast completion Q1 2028

Residential apartments

Part Endangered Ecological rehabilitation

Stage 6 forecast completion Q2 2029 

Residential apartments

Part Endangered Ecological rehabilitation

Stage 7 forecast completion Q4 2029 

Residential apartments

Part Endangered Ecological rehabilitation

Stage 8 forecast completion Q3 2030 

Residential apartments

 

The proposed Primary School and Retirement Living facility are floating stages and will come online subject to commercial negotiations with the final operators.

 

Disclaimer: Forecast completion dates are correct as at June 2021, dates outlined are subject to change due to development approvals or for other reasons outside Frasers Property‚Äôs control.