Welcome to your first construction update for The Views Release 1. We will provide you with regular updates on the progress of your land from now until settlement. These updates can be viewed within the myProsperity App, which also contains a list of the program rewards and benefits.

With bulk earthworks at The Views completed earlier in the year, our contractor Golding have established onsite and commenced works. Sewer reticulation has started and concrete sleeper retaining wall construction is also well underway, with steel posts and concrete footings being installed across the site.

As our Care Team have communicated, our contractor has been impacted by recent material shortages, which have resulted in an extension to settlement timing. Our focus remains on achieving program deadlines and we are working with our contractor to ensure we meet your revised settlement date, which is now scheduled for June 2023. 

To keep up to date with what is happening in the Brookhaven community, we invite you to join the Brookhaven Residents Group via the link below.

Congratulations again on your purchase, we look forward to welcoming you to the Brookhaven community. 

 

Neighbourhood News

Discover upcoming local events and community highlights in the Spring 2022 edition of our community newsletter, Neighbourhood News.

In the latest edition, we meet with a proactive Brookhaven mum whose aspiration is to connect new families within the community, and an avid cricket fan bringing a new junior cricket program to our community. We also share some snaps from our recent events, and showcase the generosity of our neighbourhood participating in community initiatives. Enjoy the read via the link below.

Neighbourhood News

 

Bahrs Scrub Road Network - Upgrades

In conjunction with Logan City Council, we are upgrading the local road network in Bahrs Scrub, and we are pleased to provide the following update on the progress of these significant works.

Hein Road and Menora Road – South of Berzins Court: This section of road is progressing well and entering the final stages of construction. Line-marking is currently underway, with street lights and traffic lights now commissioned. Landscaping works are well progressed, with turf, garden beds and street tree installation approaching completion. We will soon be lodging all required documentation with Council for final assessment prior to the road opening. We look forward to sharing an announcement on this with you soon.

Bahrs Scrub Road: Bulk earthworks and stormwater works are complete, with subgrade works underway. Water mains are now installed and electrical works are underway. Tarwonga Road intersection improvement has commenced, and the new roundabout is being formed. The construction of the sandstone boulder wall along existing sections of Bahrs Scrub Road is progressing well. The new extension to Bahrs Scrub Road is forecast to open in mid-2023. 