myFrasersProperty 13 38 38
myFrasersProperty 13 38 38

Shell Cove Construction Update - Dockside Homes


09 February 2024
Dockside

Dockside Homes – February 2024

Welcome to the first construction update for 2024!

We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.

This month, we’re pleased to advise that we have partnered with OpenSpace, a platform that captures on-site photography and provides an interactive view of the construction progress of your home. We hope you find this new tool valuable. Click here to take an inside view now.​

We are delighted to share the latest developments on the construction progress of the Dockside Homes. Significant milestones have been achieved.

The cladding phase has successfully concluded, with all surfaces meticulously painted and finished according to the project's design specifications. This not only enhances the visual appeal of the structure but also ensures durability against external elements.

Simultaneously, internal lining painting has commenced, breathing life into the interior spaces. The carefully chosen colour schemes are transforming the building's aesthetics, creating an inviting and vibrant atmosphere.


External finishes – Lot 6505


Internal painting commenced – Lot 6505


Internal painting commenced – Lot 6501

We are pleased to inform you that the waterproofing activities in wet areas have commenced, reinforcing these critical zones against moisture and ensuring the integrity of the building over time.

Additionally, the scaffold removal process is nearing completion, with 90% of the scaffold already dismantled. This marks a significant achievement, streamlining the construction site and paving the way for subsequent phases.


Waterproofing activities in wet areas – Lot 6503

The exterior transformation is underway with rendering to brickwork now in progress. This not only provides a protective layer to the structure but also contributes to the overall architectural character of the building. Furthermore, the installation of sunshades and feature screens has commenced, showcasing the fusion of form and function. These elements are designed not only to enhance the building's visual appeal but also to contribute to energy efficiency and occupant comfort.


Stairway - Lot 6503


Stairway - Lot 6504

Simultaneously, the installation of stairs has begun, a pivotal aspect in ensuring seamless connectivity between different levels of the structure. As we move forward, our commitment to delivering a high-quality, safe, and aesthetically pleasing project remains unwavering.

We appreciate your continued support and eager anticipation of completion. Please feel free to reach out for any additional information or queries. We look forward to sharing more positive updates in the near future.

Site Safety​

We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.


Laura Struys Customer Care Coordinator Frasers Property Australia
Silvana Stojanovski Customer Care Coordinator Frasers Property Australia

See more construction updates on



You may also like