Shell Cove Construction Update - Reflection Homes


08 May 2024

Reflection Homes – May 2024

Welcome to the latest Construction Update.

We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.

Significant progress has been achieved on the Reflection Homes project, with the recent developments:

  • The pouring of concrete slabs and termite protection installation to Lots 3109 to 3111 is ongoing, ensuring the foundation is robust and secure.
  • In Lots 3101 to 3108, the installation of ground floor frames is progressing steadily, laying the structural groundwork for these homes.
  • Window installation has commenced in Lots 3101 to 3108, marking an important step towards the completion of these homes.
  • Additionally, the laying of brickwork to the garages in Lots 3101 to 3108 has also commenced, adding both aesthetic appeal and structural integrity.


Pouring of concrete slabs continue


Brickwork commenced

It's pleasing to see the continued progress and the team remain dedicated to delivering a high-quality result. Should you have any questions or require further information, please feel free to reach out to us.

Settlement Update

We anticipate settlements to occur from Quarter 2, 2025.

Site Safety

We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.


Laura Struys Customer Care Coordinator Frasers Property Australia
Silvana Stojanovski Customer Care Coordinator Frasers Property Australia