Shell Cove Construction Update - Meridian Homes
Meridian Homes – March 2025
Welcome to the latest Construction Update.
We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.
We are excited to share the latest progress on the Meridian Homes project. Our teams have been making significant strides, and we are pleased to provide the following updates
Home 3501
- Concrete balcony has been poured, providing a solid foundation for the outdoor space.
- Sheet flooring has been installed, ensuring structural integrity for the upper level.
- Installation of the upper floor frames has commenced.
- Completed pouring the concrete wet walls for the garage.
Homes 3502–3504
- Concrete balcony has been poured, reinforcing the structural framework.
- Installation of the upper floor frames has been completed, allowing for the next construction phases.
- Craned up and commenced installing roof trusses, advancing the roof structure.
- Completed pouring the concrete wet walls for the garage.
Homes 3505–3506
- Concrete balcony has been poured, further progressing external works.
- Installation of the upper floor frames has been completed, setting the stage for roofing works.
- Installation of roof trusses has commenced, moving closer to a fully enclosed structure.
- Craned up and continued installing roof trusses, ensuring proper alignment and fit.
- Completed pouring the concrete wet walls for the garage.
Homes 3507–3508
- Windows have been installed, sealing the homes and enhancing energy efficiency.
- First courses of brickwork have been completed.
- Scaffolding for upper floor works has been set up, facilitating ongoing construction tasks.
- Completed pouring the concrete wet walls for the garage, reinforcing structural integrity.
Homes 3509–3511
- Ground floor structure has been completed, laying a strong foundation for further work.
- Windows have been installed, improving insulation and security.
- Floor joists have been completed, providing support for the upper levels.
- Completed pouring the concrete wet walls for the garage.
Home 3512
- Ground floor structure has been completed, marking significant progress.
- Windows have been installed, preparing the home for further internal work.
- Floor joists have been completed, enabling the next stages of construction.
- Completed pouring the concrete wet walls for the garage.
The Meridian Aerial View
Construction progress
Construction progress
Construction progress
Construction progress
Construction progress
Construction progress
Our team remains dedicated to delivering your home with the highest quality standards. Should you have any questions or require further information, please do not hesitate to contact our Customer Care team.
Settlement Update
We anticipate settlements to occur from Quarter 4, 2025.
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.
See more construction updates on