Shell Cove Construction Update - Meridian Homes


10 April 2025

 

Settlement Forecast: Quarter 4, 2025

On Track

Construction Progress: In progress
On Track

Welcome to the latest Construction Update.

We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community. 

We are excited to share the latest progress on the Meridian Homes project. Our teams have been making significant strides, and we are pleased to provide the following updates:

Homes 3501–3504:

  • The upper floor frames and trusses have been completed.
  • Plumbing stacks and rough-in works have commenced.
  • Upper floor window and door installation has been completed.
  • Sarking and wall flashings are complete.
  • Upper floor brickwork has been completed.

Homes 3505–3506:

  • Upper floor frames and trusses are now complete.
  • Plumbing stacks and electrical rough-in works have commenced.
  • Upper floor window and door installation has been completed.
  • Sarking and wall flashings are complete; and external façade batten installation has commenced.
  • Upper floor brickwork has been completed.
  • Box gutter, facia, and roof sheets have now been installed.

Homes 3507–3508:

  • Scaffold installation is complete.
  • First-floor sheet flooring has been installed.
  • Upper frames and trusses will commence shortly.

Homes 3509–3511:

  • Scaffold erection is complete.
  • Ground floor brickwork has commenced.
  • Sheet flooring, upper frames and trusses are scheduled to commence shortly.

Home 3512:

  • Commenced the scaffold installation.
  • Ground floor brickwork has commenced.
  • Sheet flooring, upper frames and trusses are due to commence shortly.

Our team remains dedicated to delivering your home with the highest quality standards. Should you have any questions or require further information, please do not hesitate to contact our Customer Care team.

 


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

Our team remains dedicated to delivering your home with the highest quality standards. Should you have any questions or require further information, please do not hesitate to contact our Customer Care team.

Site Safety

We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.


Silvana Stojanovski Customer Care Coordinator Frasers Property Australia