myFrasersProperty 13 38 38
myFrasersProperty 13 38 38

Berwick Waters Construction Update - Stage 14


17 August 2023

Construction Update

Welcome to the latest Berwick Waters Construction Update.

We’re excited to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.

Construction Progress

We're pleased to advise that the base layer of the roads is now complete and gas and water works are underway.

Over the coming weeks kerb and channel works will commence.

Track your property anytime, anywhere on our new myFrasersProperty app. See more: https://www.frasersproperty.com.au/Care-and-Rewards/MyFrasersProperty

Settlement Forecast

Settlement of your land is now anticipated in March - May 2024.

Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Helpful Links
Builder Information
Berwick Waters Facebook Page
Berwick Waters Community Page
Meet & Greet

We're available to discuss any questions or concerns you may have regarding your coming settlement.

Book your appointment now

If you have any queries at all regarding settlement, we encourage you to get in touch!


See more construction updates on



You may also like