Berwick Waters Construction Update - Stage 17


18 September 2025

 

Settlements Forecast: Jun 2026 – Aug 2026

On Track

Construction Milestone: Services
On Track

Civil works in Stage 17 are progressing well. Installation of the sewer is complete and drainage works are now underway and will be the focus over the next month.