Berwick Waters Construction Update - Stage 19
- Settlements Forecast: Feb - Mar 2027
On Track
- Construction Milestone: Bulk Earthworks
-
On Track
Roads and Drainage Works Completion
We’re excited to share that sewers and drainage works are now complete. These steps are crucial for ensuring sanitation and public health, as well as to prevent flood and protect your property and all the infrastructure in your community.Watermain Underway and Pavement Underway
The watermain is on track to be laid by the end of this week, with class 3 pavement works completed.Kerb Installation Commencing
Kerb Installation is also scheduled to commence in the coming weeks to ensure a well-designed road infrastructure and safety.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on