Five Farms Construction Update - Stage 10
- Settlement Forecast: Late Q1 to Early Q2 2027
-
-
Construction Milestone: Road works
-
We're pleased to share that pavement stabilisation and sewer main installation have now been completed, with construction continuing to progress well across the stage.
Road and easement drainage works are currently underway and are expected to be completed within the next few weeks.
The next phase of works will include the installation of subsurface drainage and road crossing conduits, helping prepare the stage for future road and service infrastructure.
For key highlights, important next steps and information for purchasers and builders, please visit our Builder Information page.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on