Berwick Waters Construction Update - Stage 16
- Settlements Commenced 11th August 2025
On Track
- Construction Milestone: Titled
-
On Track
We’re thrilled to welcome the Stage 16 residents into the development following the registration of the Plan of Subdivision on 28th July, which led to settlements commencing on 11th August.
An electrical asset needs to be lowered before we can complete the final works on the Radiant Boulevard Bridge and we now expect it to open in late October.
You can access your titled Stage 16 lot via Laker Boulevard.
Our landscape contractor has commenced works and plans to complete all works prior to the end of November.
Your ‘Meet Your Neighbour’ event for Stage 16 is on Saturday 11th October from 1–3pm. The event invite was sent via email and SMS, please contact your Customer Care Consultant, Cirilla, if you haven’t received your invite.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on