Five Farms Construction Update – Stage 28
- Settlement Forecast: June 2025
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.- Construction Milestone: Authority Approvals
-
On Track
Construction works are now complete, and we are working with the respective authorities to obtain approval for Statement of Compliance consent.
Prior to obtaining Statement of Compliance on Stage 28, the Precinct 2 Temporary Retarding Basin needs to be constructed, and acceptance of works granted. Construction works on the Precinct 2 Temporary Retarding Basin are progressing well and are scheduled for completion in late May 2025.
In the meantime, you're welcome to arrange for your builder to carry out soil testing on your lot.
If your finance isn't finalised yet, we strongly recommend reaching out to your Conveyancer and/or Lender to discuss your settlement requirements, valuation inspections can be booked now. This will help ensure a seamless journey to becoming a landowner.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on