Mambourin Construction Update - Stage 36B
- Settlement Forecast: September 2026
-
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction Progress: Roadworks & Auditing
-
On Track
Road works are complete, including asphalt surfacing, signage, line marking, and final site clean-up in preparation for the Stage to be open.
Water and sewer infrastructure works have been completed, with all testing finalised and water quality results successfully returned.
The auditing process for the electrical connections is currently underway. Final testing and verification of the completed infrastructure are expected to be completed in the coming weeks.
Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on