Track your Property

To assist you on your property journey we have developed this tracker that can guide you on all the important milestones from when you sign the contract, to construction and reaching a settlement and beyond. Click on the phases below or click and drag left and right to scroll through the milestones.



Disclaimer: Whilst Frasers Property has tried to ensure that the tracking status is up to date, the content provided is ‘as is’ and ‘as available’ and is subject to change.

Planned Settlement: Q4 2025

Pioneer Townhomes 1A

Homes 101–110
  • Joinery installation is complete
  • Tiling is nearing completion
  • Stone benchtops are scheduled for installation by the end of April
  • External hardscaping works have commenced
Homes 133–136
  • Painting is currently in progress
  • Waterproofing has commenced
  • Scaffolding has been stripped
Homes 126–132
  • Painting and waterproofing is complete
  • Tiling works are underway
  • Scaffolding has been stripped
Homes 137-138
  • Painting and waterproofing is complete
  • Tiling works are underway
  • Scaffolding has been stripped
Latest Construction Update