Midtown Macquarie Park Primary School: February 2026 Update


26 February 2026

The new primary school for Midtown Macquarie Park is progressing well, bringing our community closer to a modern local school designed for up to 750 students from Kindergarten to Year 6.

Construction Highlights

  • Façade works are almost complete, with scaffolding scheduled to come down in early March.
  • Internal walls and ceilings across all levels are nearing completion.
  • The tower crane has now been removed, and joinery installation will commence in March.

These milestones mark a major shift from structural works to the interior fit‑out.

Intake Area & Enrolments

The school’s intake area has been officially confirmed. Families can check their address via School Finder

Enrolments are expected to open March 2026 for students from Kindergarten to Year 6.

You can also help shape the school’s values, motto, uniform and logo. Survey link

(Survey takes 5 minutes of your time, closed 2 April 2026)

Midtown school intake
Map showing enrolment intake area

What’s Coming Up

In the next few weeks, residents will see:

  • Final façade works
  • Scaffolding removal
  • Interior joinery fit‑outs beginning