Brookhaven Construction Update - The Crossing Release One


15 September 2025

 

Settlement Forecast: Q1 2026

On Track

Settlements for The Crossing Release One are scheduled for Q1 2026.

Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Progress: Bulk Earthworks
Commenced

On site works are officially underway for The Crossing Release One. Site clearing and mulching is now complete. Machinery has been mobilised on site and the bulk earthworks is progressing well. Preparation for civil construction to commence including retaining walls and services is underway.

Along Bahrs Scrub Road, box culvert construction continues on the Eastern and Western entrance after landing last month. Stormwater is underway and progressing well, and water reticulation is scheduled to commence shortly. Moving forward in the program, service installation will continue including the completion of stormwater and water, and commencement of electrical.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.

Get in touch


See more construction updates on



You may also like