Brookhaven Construction Update - The Crossing Release One
- Settlement Forecast: Q2, 2026
-
Delayed
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.
- Construction Progress: Services
-
Commenced
The bulk earthworks scope has progressed well and is nearing completion. The civil scope is now well under way, with sewer reticulation nearing completion and stormwater reticulation underway. Retaining wall construction scheduled to commence.
Along Bahrs Scrub Road, road preparation works are nearing completion and asphalt is scheduled. Footpath and landscaping works are also underway. Moving forward in the program, the team will be completing testing and finishing works, in preparation for Bahrs Scrub Rd opening.
These construction programs have been impacted by the recently experienced wet weather.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on