Berwick Waters Construction Update - Stage 20
- Settlements Forecast: August 2026 – September 2026
On Track
- Construction Milestone: Services
-
On Track
Civil works in Stage 20 are progressing well and are on track with the original program dates. Installation of the drainage and sewer are now complete.
The construction of the first layer of the road pavement is underway and will be completed in early 2026.
In the new year, the second layer of road pavement will commence and kerb (gutters) to follow.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on