Berwick Waters Construction Update - Stage 20
- Settlements Forecast: Aug 2026 – Sep 2026
On Track
- Construction Milestone: Services
-
On Track
Civil works in Stage 20 are progressing well and remain on track in accordance with the original program schedule.
The watermain assets are now complete.
The construction of the kerb and power assets is to commence in the coming weeks.