Five Farms Construction Update - Stage 7
- Settlement Forecast: June-July 2026
-
-
Construction Milestone: Roadworks and Services
-
Works are progressing well on site, with watermains, subsurface drainage, class 3 road pavement, kerb and base course asphalt now complete, with electrical trenching and cable installation currently under construction.
The Contractor will then focus on installing telecommunications and footpath over the coming weeks.