Mambourin Green Construction Update - Stage 3


19 March 2026

 

Settlement Forecast: June – July 2026

On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Progress: Roadworks and Services
On Track

Electrical reticulation works were impacted by wet weather delays, and we’re pleased to advise these works are now nearing completion. This infrastructure is essential for delivering power to future homes.

Communication reticulation works, including the installation of Opticomm infrastructure, are set to commence next. These works establish the pathways required for future fibre connections, ensuring homes will be equipped for high-speed internet and modern digital services.

Concrete works including footpaths and driveway crossovers are scheduled to commence following completion of communication reticulation works. These works will help define safe pedestrian routes and establish the formal access points that will serve future homes, supporting both functionality and connectivity across the development.

Track your property anytime, anywhere on our new myFrasersProperty app.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.


See more construction updates on



You may also like