Mambourin Green Construction Update - Stage 3


21 May 2026

 

Settlement Forecast: June – July 2026

On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Progress: Roadworks and Services
On Track

We’re pleased to advise that concrete works, involving footpaths and driveway crossovers, are nearing completion, marking another key step in shaping the pedestrian network and supporting access to future homes.

Topsoiling works across nature strips and residential lots are following closely behind, preparing the ground for upcoming landscaping works that will occur following Statement of Compliance.

Final road pavement works are scheduled to commence shortly. This phase includes the final asphalt layer.

Track your property anytime, anywhere on our new myFrasersProperty app.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.