Baldivis Grove Construction Update - Stage 9


29 May 2025

 

Certificates of Title Planned – July 2025

On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Milestone: In Progress
On Track

With construction nearing completion for Stage 9, road works have now commenced and expected to be completed by the end of May.

Design works for the park are nearing completion, engaging local indigenous artists to provide artworks to be incorporated into the parklands within Stage 9. We are very excited to share with our community the work that incorporates the rich history of this site.


Welcome to our May Community Update!

Discover all of the exciting events and activities coming up in June and find out how construction works are progressing within Baldivis Grove.

Baldivis & Districts Men's Shed

Updates on the Baldivis & Districts Men’s Shed due to be built on the corner of Pike and Eighty Road can be found through the monthly City of Rockingham bulletin on this project. The Corporate and Community Development Agenda is available on the City’s website here. Updates on the Men’s Shed project are included on pages 596 and 597.

Get ready to FOGO like a pro!

The City of Rockingham is delivering the FOGO ready kits to households ready for first collections at the end of June 2025. Keep your eye out for yours arriving soon! They are also hosting some information sessions – you can go along and find out what the new service means for you 🌱🚛 “Keeping your food waste out of landfill has never been easier!”

Session times and locations:

🗓️ 7 June, 7am–12pm – Baldivis Lions Community Market (No registration required)
🗓️ 11 June, 6.30–7.30pm – Mary Davies Library and Community Centre
🗓️ 18 June, 6.30–7.30pm – Gary Holland Community Centre

Spaces are limited. Head to rockingham.wa.gov.au/FOGO to register or to find out where we will be popping up an info stall near you.

Baldivis Children’s Forest upcoming Activities and Adventures

June 4th - Build a Nest Box with Re-Cyc-Ology

Spaces are limited, so grab your ticket now and help us create a brighter future for Perth’s wildlife. Together, we can make hollows happen! More information here: https://www.facebook.com/share/16NAFtKRpi/.

*Rockingham residents, please book through the City of Rockingham's website to receive your 50% discount.

July 19th – Mud Kitchens and Loose parts Play in Nature.

Let imaginations run wild in a morning of open-ended, nature-based play! Stir up forest stew in the mud kitchen, build wild contraptions, or simply follow curiosity wherever it leads.

More information here: https://www.facebook.com/share/1AWacYtuqe/.

Tamworth Wetlands Parkrun – move and make friends!

Every Saturday at 8:00am. A free, fun, and friendly weekly 5k community event. Walk, jog, run, volunteer or spectate – it's up to you! Every week they grab a post parkrun coffee in the Dome Café on Settlers Ave - please come and join in! More details and how to register here: https://www.parkrun.com.au/tamworthwetlands/.

General Works in the Community

Stage 9 Parkland

Delivery of the central park to connect to the existing green space is due for completion in December 2025.

Stage 9 Land Lots

This final stage is currently under construction and progressing well. Construction is due for completion in July.

Lots 383 and 384

Construction of 2 lots are underway, located to the western end of Thornton and Gibberd Street. Completion of these 2 lots hail the end of all land lot developments within the estate.

Stage 10 - Energisation

Western Power have advised that energisation of this stage is programmed for early June 2025.

As always, if you have ideas about how you’d like to build community reach out to our community team today on communityWA@frasersproperty.com.au.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.