Ed.Square Construction Update - Block E North
- Settlement Forecast: July 2025
On Track
We anticipate the completion of Brooklyn Row E North Townhomes in early July 2025.
- Construction Progress: In progress
-
On Track
We are pleased to bring you our next construction update for your new home in Brooklyn Row Block E North.
Since our last update, we have continued to see these homes progress, with external works being a strong focus now.
Lots 13121-13132: In the eastern wing, the final coats of paint are underway, initial cleans have commenced and final caulking to wet areas is advancing well. Quality assurance inspections and commissioning has also commenced.
Lots 13133-13144: In the western wing, the internal fitout is almost complete. This will see initial cleans commence along with final caulking to wet areas. Quality assurance inspections will commence shortly.
In the rear courtyards of both wings, waterproofing to the podiums is complete and tile installation is well advanced. Planter boxes have soil installed and fencing installation has commenced.
On the outside of the site, bricklayers have completed bin bays to western façade and services connections have been completed. This has seen our landscapers install footpaths and start installing subgrade for paving to courtyards. Eastern façade paving to courtyards is nearly complete and preparation to the Mews is nearing completion. Once hard scaping is complete the team will start with soft scapes in the coming week.
It is currently anticipated that settlement of your new home will commence in July 2025.
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
If you have any queries, do not hesitate to reach out to the Customer Care Team at CustomerCareNSW@frasersproperty.com.au or by calling 13 86 88.
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.
See more construction updates on