Ed.Square Construction Update - Central Park Greenway Collection
Our building contractor, Patterson Building Group, continues to make strong progress on site, with homes now at various stages of construction as outlined below:
Manhattan Terraces (CN0501-CN0505)
Roof truss installation is well underway across these homes. Fascia and gutter installation will commence shortly in preparation for the installation of roof sheeting.
Manhattan Terraces (CN0506-CN0510)
Ground and first floor framing has now been completed. Brickwork is progressing around the building perimeter, and service trades have commenced preparations for rough-in works.
SOHO Terraces (CN0511-CN0515)
Roofing has been completed and cladding installation is well advanced. Service rough-in works and insulation installation have been completed, with internal wall linings now underway.
SOHO Terraces (CN0516-CN0520)
Ground and first floor framing has now been completed. Brickwork is progressing around the building perimeter, and service trades have commenced preparations for rough-in works.
At this stage, settlement of your new home is anticipated to occur in mid-2027. We will continue to keep you informed as construction progresses.
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.
If you have any queries, do not hesitate to reach out to the Customer Care Team at CustomerCareNSW@frasersproperty.com.au or by calling 13 86 88.
See more construction updates on