Brookhaven Construction Update - The Sanctuary Release One
- Settlement Forecast: Late Q3 2025
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.
- Construction Progress: Bulk Earth Works
-
On Track
Despite the wet weather, Golding Contractors have made steady progress with export activities. Bulk earthworks are almost finished, with trench excavation and the installation of concrete sleeper retaining walls currently underway. Internal sewer pipes are being laid, and manholes are under construction.
Work along Bahrs Scrub Road has gained significant momentum following the full closure. New temporary powerlines have been installed, and drilling for other underground services is in progress. Excavation in the waterway has started, enabling us to accelerate to culvert construction.
In the coming month, the Golding team will complete bulk earthworks and export activities, whilst continuing to construct the sewer and stormwater infrastructure.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on