Brookhaven Construction Update - The Sanctuary Release One


29 May 2025

 

Settlement Forecast: Late Q3 2025

On Track

Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Progress: Bulk Earth Works
Commenced

The Sanctuary Release One is progressing steadily, with the site team maintaining momentum despite challenging weather conditions. Concrete sleeper retaining walls are nearing completion, with final I-beams being installed. Exporting activities are now completed, with our sewer network and stormwater reticulation now underway.

Along Bahrs Scrub Road, the first section of box culverts was successfully landed in May, and construction of the culverts, along with earthworks, is progressing well. A significant cut of the existing road is planned for June, which will create a level access into the Sanctuary Release One.

Looking ahead, the team is set to commence the construction of boulder walls and water reticulation, with electrical and communications following closely behind.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.

Get in touch


See more construction updates on



You may also like