Brookhaven Construction Update - The Sanctuary Release Two
- Settlement Forecast: Early Q4 2025
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.
- Construction Progress: Bulk Earth Works
-
On Track
Golding Contractors have made steady progress despite the wet end to April.
Bulk earthworks have continued, with large volumes of fill being exported off-site. Drilling for retaining walls is well underway, and concrete sleeper walls are currently being installed. Trench excavation for internal services has also begun.
Along Bahrs Scrub Road, progress has accelerated since the full closure. Temporary powerlines have been successfully installed, and drilling for additional underground services is ongoing. Excavation in the waterway has commenced, helping to speed up the culvert construction process.
Looking ahead, the Golding team plans to continue bulk earthworks and exporting activities in the coming month. Installation of concrete sleeper retaining walls will progress, and sewer and stormwater reticulation are set to begin.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on