Brookhaven Construction Update - The Sanctuary Release Two
- Settlement Forecast: Early Q4 2025
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.
- Construction Progress: Bulk Earth Works
-
Commenced
Progress on site has remained steady despite the consistent wet weather this month. Export activities continue with large volumes of material being carted off-site, ensuring earthworks can continue efficiently. Concrete sleeper retaining walls are progressing as planned, with I-beams being drilled and sleepers being stockpiled onsite. Blasting and excavation for services have commenced, with pipe laying forecast in the coming month, marking a key milestone in infrastructure delivery.
Along Bahrs Scrub Road, the first section of box culverts was successfully landed in May, and construction of the culverts, along with earthworks, is progressing well. A significant cut of the existing road is planned for June, which will create a level entry into Sanctuary Release Two.
Over the coming months, blasting and service excavation will continue, while pipe laying progresses. The construction of concrete sleeper retaining walls will continue as planned, with final earthworks and export scheduled for completion.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on