Brookhaven Construction Update - The Sanctuary Release Two
- Settlement Forecast: October/November 2025
On Track
Settlements for The Sanctuary Release Two are on track to commence in October/November 2025. Initially, there will be staged access to the land following settlement. Frasers Property will provide additional details regarding this in the coming weeks.
Settlement for Lots 1907, 1908, 1909 has been delayed to Q1, 2026 and the buyers of these lots will be updated accordingly.
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.
- Construction Progress: Bulk Earthworks
-
Commenced
The Sanctuary Release Two is progressing steadily with export activities almost complete and installation of concrete sleeper retaining walls continuing. Blasting and excavation for services is complete which has allowed sewer reticulation to commence.
Along Bahrs Scrub Road, box culvert construction continues, following the first section being placed in May. Earthworks and export have progressed well, with retaining walls and sewer reticulation to follow.
Moving forward in the program, the team is scheduled to commence construction of water reticulation, electrical and communications, and roadwork preparation from next month.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on