The Quarry Construction Update – Release Four
- Settlement Forecast: August 2025
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.- Construction Progress: Construction Commenced
-
On Track
Welcome to your latest construction update for Release Four at The Quarry.
We’re pleased to report that construction is progressing steadily on Stage 4, despite some recent delays due to wet weather.
Inter-allotment retaining walls are now nearing completion, with sewer and stormwater infrastructure expected to be finalised shortly.
Following this, works will transition to the road network, which remains on track for completion in early July 2025. This will pave the way for landscaping and electrical installations to begin.
At this stage, settlements are still anticipated to commence in August 2025, in line with the current construction timeline.
If you have any questions in the meantime, please don’t hesitate to contact our Customer Care team using the details below.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on