Five Farms Construction Update - Stage 30


27 March 2026

 

Settlement Forecast: June-July 2026

 

Construction Milestone: Roadworks and Services

Installation of watermains, subsurface drainage, the first layer of road pavement, and kerb are now complete. The Contractor is currently focussing on installing the remainder of the road pavement, asphalt and electrical trenching for cabling.

Once the above is complete, the Contractor will move onto installing telecommunications and footpath.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.


Customer Care VIC Frasers Property Australia

See more construction updates on



You may also like