Mambourin Green Construction Update - Stage 6
- Settlement Forecast: Q4 2026
-
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction Progress: Bulk Earthworks
-
On Track
Welcome to the latest Mambourin Green Construction Update.
We’re pleased to inform that the functional layout has been approved, allowing the team to move ahead with detailed planning.
Detailed design plans are being finalised and are expected to be submitted to Council in November.
Civil construction works have gone out to tender, with a contractor expected to be appointed in December.
Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on