Mambourin Green Construction Update - Stage 6


19 November 2026

 

Settlement Forecast: March 2027

On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Progress: Services and Roadworks
On Track

Kerbs are Complete
Kerb works are now complete, defining the road alignment and establishing the drainage edges of the future street network. The completed kerbs also provide the framework for the remaining civil infrastructure works, including road pavement and footpath construction.

Electrical Trenching Underway
Electrical trenching is almost complete, with excavations progressing to the required depths in preparation for the installation of underground conduits and electrical cabling.

Concrete Footpath Works Underway
Concrete footpaths are being laid on one side of the street, while electrical and connection works progress on the other. Running these activities at the same time keeps our construction team moving efficiently and minimises delivery timelines.

Track your property anytime, anywhere on our new myFrasersProperty app.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.


See more construction updates on



You may also like