Mambourin Green Construction Update - Stage 6
- Settlement Forecast: Q4 2026
-
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction Progress: Bulk Earthworks
-
On Track
Early sewer works have been approved by Council and are scheduled to commence in January. These works are a key step in preparing the site for future stages and will help ensure essential services are ready ahead of the main civil works.
The civil construction tender was issued in November, and we are now in the final stages of appointing a contractor. We anticipate awarding the contract in December, which will allow us to start major works early in the new year.
Detailed design for the stage has been lodged with Council, and we expect approval in January. This is an important milestone that ensures all technical plans for roads, drainage, and services are in place before construction begins.
Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on