Planned Settlement: Q4 2025

Pioneer Townhomes 1A

Homes 101–110: The fencing posts have been successfully installed, stepping stone work is currently underway, and our internal final defect inspections are in progress to ensure everything is in order.
Homes 133–136: Landscaping works are well underway, fencing posts have been installed, and all services fit-off has been completed, marking great progress on-site.
Homes 126–132: Flooring has been completed, benchtops are now installed, and the services fit-off is finished—bringing us another step closer to completion.
Homes 137-138: The joinery is complete, timber flooring has been beautifully installed, and the painting work is now finished—everything is really coming together.
Latest Construction Update