Mambourin Green Construction Update - Stage 1


13 November 2025

 

Settlement Forecast: March 2026

On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Progress: Roadworks and Services
On Track

Welcome to the latest Mambourin Green Construction Update.

We’re pleased to inform that subbase FCR (fine crushed rock) works for the lower road pavement has now been completed. This marks a key milestone in delivering internal infrastructure and improving site accessibility.

Kerb and channel works have commenced and are progressing well, with completion anticipated shortly. This phase marks an exciting step in the civil construction process, helping to define the final road layout while supporting essential drainage infrastructure.

Electrical reticulation works are scheduled to commence shortly, marking an important step in preparing the development for future services. This phase involves installing underground electrical infrastructure that will safely and efficiently distribute power across the site.

Track your property anytime, anywhere on our new myFrasersProperty app.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.


See more construction updates on



You may also like