Mambourin Green Construction Update - Stage 4
- Settlement Forecast: Q3 2026
-
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction Progress: Roadworks and Services
-
On Track
Welcome to the latest Mambourin Green Construction Update.
We’re pleased to advise that drainage works have now commenced, which involves the installation of underground stormwater infrastructure designed to manage rainwater effectively and support long-term site performance.
The next phase of works will involve road boxing, subgrade preparation, and the placement of the construction layer. These tasks are essential for building a strong and stable foundation for future roads and areas.
Water reticulation works (water mains) are scheduled to commence following the completion of the construction layer. This phase will involve installing water mains to support the delivery of reliable residential water supply across the site.
Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on