Mambourin Green Construction Update - Stage 4
- Settlement Forecast: 22 September 2026
-
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction Progress: Registration of Titles
-
On Track
Roads and Drainage Works Completion
Road and drainage works have now been completed, including asphalt surfacing, line marking and final site clean-up, preparing the neighbourhood for residents to move in and begin building their homes.Statement of Compliance
Statements of Compliance has been received for all services and from the Council.Settlements commencing 22 September
Following the completion of all works and Authority approvals, Titles are now registered and settlements will be commencing 22 September.Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on