Mambourin Green Construction Update - Stage 4
- Settlement Forecast: September 2026
-
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction Progress: Roadworks and Services
-
On Track
Electrical Works Underway
Electrical trenching works have now been completed across the stage, with electrical reticulation and communication infrastructure works currently progressing as service installation continues.Kerb and Road Works Complete
Kerb and channel construction, along with the first layer of asphalt, has now been completed, marking another key milestone in the delivery of the stage.Settlements Expected in Early September
Subject to final approvals and completion of remaining infrastructure works, settlements remain on track for early September.Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on