Mambourin Green Construction Update - Stage 5
- Settlement Forecast: Q4 2026
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.- Construction Progress: Bulk Earthworks
-
On Track
Welcome to the latest Mambourin Green Construction Update.
Detailed design has been submitted to Council for approval, marking a key milestone toward construction commencement.
Civil construction works tender are now issued with contractor appointment expected in December. Civil works are anticipated to commence December, pending approvals.
Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on