Mambourin Green Construction Update - Stage 5
- Settlement Forecast: Q1 2027
-
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction Progress: Services
-
On Track
Detailed design is now approved
We are pleased to confirm that the detailed design for Stage 5 has now been formally approved. This milestone confirms that all technical design requirements have been met and allows construction activities to progress in accordance with the approved plans.Drainage works have commenced
Drainage infrastructure works are now underway. These works form a critical early component of civil construction, establishing the underground stormwater network required to support future roads and services.Services reticulation works to follow in the coming months
Over the coming months, construction will continue to progress with water, electrical and communications reticulation works to begin. These works will deliver the essential services required to support future homes within Stage 5.Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on