Mambourin Green Construction Update - Stage 5
- Settlement Forecast: Q1 2027
-
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction Progress: Services
-
On Track
Drainage works are almost complete. Drainage infrastructure forms a critical part of early civil construction, establishing the underground stormwater network.
Road excavation and subgrade works will follow drainage completion. These works create the base structure for future road pavements.
Water reticulation works including the installation of water mains, are scheduled to commence in July. These works will provide a reliable water supply to future homes.
Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on