Mambourin Green Construction Update - Stage 5
- Settlement Forecast: Q1 2027
-
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction Progress: Roadworks & Services
-
On Track
Road Crossing Conduit Installations Complete
Road crossing conduits and underground service conduits have now been installed, connecting future services around the development.Road Pavement Works Underway
Following completion of the capping layer, the construction team is now installing the crushed rock pavement layer throughout the road network. These works continue to advance the roads towards the final asphalt stage.Kerb Works will Commence Shortly
The next stage of construction will see kerb works commence across Stage 5. These works will help define the future road network and continue shaping the streetscape for future residents.Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on