Mambourin Green Construction Update - Stage 4
- Settlement Forecast: Q3 2026
-
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction Progress: Roadworks and Services
-
On Track
Drainage trenching and pipe installation have been impacted by recent wet weather conditions. However, works are progressing and now nearing completion, with additional crews onsite to support delivery. This is essential stormwater infrastructure, designed to manage rainwater effectively and support long-term site performance.
Lower road pavement works are set to commence shortly. This includes road boxing, subgrade preparation, and placement of the construction layer – all essential steps in building a strong and stable foundation for future roads and shared spaces.
Water reticulation works are scheduled to commence mid-January 2026. This phase will involve installing water mains to ensure reliable and efficient water supply across the site.
Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on