Mambourin Green Construction Update - Stage 5
- Settlement Forecast: Q4 2026
-
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction Progress: Bulk Earthworks
-
On Track
The detailed design for Stage 5 has been lodged with Council, and we’re expecting formal approval shortly. This is a key milestone that keeps construction timeframes on track and allows works to move smoothly into the next phase.
We’ve received the civil construction tender and are in the final stages of assessment. The contract is expected to be awarded imminently, enabling our contractor to mobilise and commence on‑ground works soon after.
Early approval has been secured for the sewer works, with construction scheduled to begin on 19 January. These early works help establish the essential service infrastructure for the stage and support timely delivery of the broader construction program.
Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on