Mambourin Green Construction Update - Stage 5
- Settlement Forecast: Q4 2026
-
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction Progress: Bulk Earthworks
-
On Track
The detailed design for Stage 5 is expected to be finalised this week, after which it will progress through Council approval. This package contains the technical engineering plans required before major construction can begin, helping ensure works can move smoothly into the next phase once approved.
The civil construction contracts are currently being executed with the contractor preparing to commence. Awarding the tender is a key milestone - it means the builder responsible for delivering the roads, drainage, services and general civil works has been locked in.
Early sewer works commenced at the end of January and are now well underway. These early works install essential underground sewer infrastructure for the stage. Completing this early ensures important services are in place and helps keep the broader construction program on track.
Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on