Mambourin Green Construction Update - Stage 4
- Settlement Forecast: Q3 2026
-
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction Progress: Roadworks and Services
-
On Track
We’re pleased to advise that water reticulation works are now complete. This milestone involved the installation of water mains to ensure reliable and efficient water supply throughout the development.
Road crossing conduit works are also complete. This marks a key step toward enabling seamless service connections across the site and supports the integration of essential infrastructure.
Capping layer works have now commenced. This phase involves placing and compacting a layer of crushed rock to form a stable base for the internal road network. It marks a step toward lower road pavement construction and improves site access as the development progresses.
AG drains installation is set to commence soon. These works are a part of the underground drainage network that protects the road pavement and allows water to freely drain away.
Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on